Griffin DewateringSLC Airport Central Tunnel

Dewatering and Groundwater control experts and have been since 1934. From manufacturing quality equipment to providing effective construction dewatering services, their field of operations, hydrology, and engineering teams have done it all. Most importantly, they have earned a reputation for keeping construction projects safe and on-schedule, minimizing risk while maximizing peace of mind.

Tunnel construction project requiring 35 ft. deep excavation, depressurization, and dewatering of underlying soils.

Griffin provided a turn-key solution and completed all dewatering permitting, design, submittal, and installation. Griffin’s deep well system design was optimized for the difficult dewatering conditions at the site. Griffin worked with the Client to develop the best value dewatering and treatment plan that incorporated construction groundwater control with the safe removal of groundwater contaminants. Griffin was able to successfully design, install, monitor, and remove the full system while allowing the Client to meet their goal. Griffin overcame these challenges by using our vast experience, the knowledge of our treatment and design teams, and our superior operations team.

Download the SLC Airport Central Tunnel case study below:

DEWATERING & GROUNDWATER CONTROL EXPERTS SINCE 1934.

Griffin offers dewatering and water treatment services for a wide variety of applications. Deep expertise allows us to develop and implement the most effective solutions for any groundwater challenge. View our services below.

Related articles

Case Studies / 20 October 2023

Sustainability Excellence Company of the Year – TDI Award Winner.

Case Studies / 17 October 2023

Wells / Drilling Project of the Year – TDI Award Winner.

Case Studies / 25 September 2023

Dewatering Consultant Project of the Year – TDI Award Winner.

Case Studies / 15 September 2023

Dewatering Contractor Project of the Year – TDI Award Finalist.

Case Studies / 12 September 2023

Equipment or Material Innovation of the Year – TDI Award Winner.

Case Studies / 5 September 2023

Dewatering Contractor Project of the Year – TDI Award Winner.